Bicycle Plan and Pedestrian Infrastructure
Bicycle Plan
The Bicycle Plan was adopted by the Jefferson County Planning Commission June 2012. The plan was designed to serve as the blueprint for making improvements to the county’s bicycle network. The existing multi-modal transportation system will be enhanced through the implementation of safe and convenient on-street and off-street facilities. These planning processes utilized a regional approach that focuses on the implementation of bicycle accommodations that are continuous and consistent throughout the cities, towns, and unincorporated areas of Jefferson County. A more extensive bicycle network will help the county achieve its goal of increasing the number of bike and walk trips.

Jefferson County received a Transportation Improvement Program Grant to update the county’s bike plan, and selected Toole Design Group to lead the project. More information will be posted here as this project develops.

See Bicycle Plan Updates

Schedule:
The Bicycle Plan is anticipated to be completed by early 2022. Important project stages are highlighted below.

Spring 2021:
  • Stakeholder meetings
  • Board of County Commissioners Staff Briefing
  • Finalize Public Engagement Plan
Summer 2021:
  • Stakeholder meeting
  • Creation of network map
  • Public engagement activities
  • Jefferson County Planning Commission meeting
Fall 2021:
  • Public engagement activities
  • Stakeholder meeting
  • Jefferson County Planning Commission meeting
  • Creation of Facility Design Guide
  • Street and Road Template Updates
Winter 2021 / 2022:
  • Public engagement activities
  • Stakeholder meeting
  • Jefferson County Planning Commission meeting
  • Final Bicycle Plan completed
Pedestrian Infrastructure
Please reference the Major Thoroughfare Plan for Roadway Templates; roadways assigned a Street Template have or are planned to have sidewalks.

Evergreen Trails Master Plan
Finalized in December 2015, the Evergreen Trails Master Plan (PDF) is a grant-funded project to establish the vision of a cohesive trail network in the core of the Evergreen community. The Plan details a network of trails and on-street bicycle and pedestrian facilities that links Evergreen’s parks, open space, schools, and community assets. While the Plan is not a county-adopted planning document, it is a community-vetted reference that prioritizes near-term and long-term phased implementation of recommended improvement projects to increase mobility and recreational options and to improve access, safety and comfort for the community.

For additional information on any Jefferson County bicycle and/or pedestrian planning documents, please contact Yelena Onnen at 303-271-8497.

Calendar

Tue Aug. 3 Jeffco Bike Plan Virtual Open House #1
Thu Aug. 5 Jeffco Bike Plan Virtual Open House #2
Wed Oct. 13 JEFFTAAG and Jeffco Forum Meeting

Bicycle & Pedestrian Plan Documents: www.jeffco.us/2867/Bicycle-Plan-and-Pedestrian-Infrastructu

The ultimate arbiter is the people of the Union. ~ Thomas Jefferson
Voting is the foundation act that breathes life into the principle of the consent of the governed. ~DeForest Soaries
Political Calendar

Please Log in or Create an account to join the conversation.

Time to create page: 0.145 seconds
Powered by Kunena Forum
sponsors
© My Mountain Town (new)
Google+